Whole-Home Renovation in Leander, TX: 2026 Cost Guide
A down-to-studs whole-home renovation in Leander typically lands between $250,000 and $450,000 for a 2,000–2,500 sq ft house, with lighter whole-house projects that keep the existing layout running $150,000–$250,000 and high-end work with custom millwork and moved walls going past $450,000. Construction runs 4 to 8 months once demolition starts, and design plus permitting happen before that. Home Remodel Pro puts the whole thing on one contract, one schedule and one fixed price in writing before a single wall comes down.
Already planning a whole-home renovation? Get a real price for your house →

What a Whole-Home Renovation Costs in Leander
Whole-home pricing is driven by three things: how much of the house gets opened up, whether plumbing and electrical move, and the finish level you pick. A renovation that keeps every wall and every fixture location where it is costs far less per square foot than one where the kitchen moves to the back of the house and two bathrooms get re-piped.
Here is how the ranges usually break down on a typical Leander house of 1,800 to 2,800 square feet. These are whole-house numbers that include the kitchen, the bathrooms, flooring throughout, paint, trim, lighting and electrical updates.
Inside those numbers, our published Austin-area kitchen ranges still apply: $45,000–$70,000 for a refresh in the existing footprint with new cabinets, counters, lighting and fixtures; $70,000–$110,000 when the layout opens up and plumbing moves; and $110,000+ for a high-end kitchen taken to the studs with custom cabinetry and high-end appliances. Bathrooms inside a whole-home project typically run $25,000–$45,000 for a primary suite and $15,000–$25,000 for a secondary bath.
- $150,000–$250,000 — whole-house cosmetic-to-moderate: all new flooring, paint, trim and doors, refreshed kitchen and baths in their existing footprints, new lighting and fixtures, no layout changes.
- $250,000–$450,000 — true down-to-studs: drywall off, new electrical and plumbing distribution, HVAC replacement or redesign, windows, insulation, relocated kitchen or bath fixtures, new cabinetry throughout.
- $450,000+ — high-end: custom cabinetry and millwork in every room, stone slab surfaces, steel or glass openings, high-end appliances, significant structural changes designed by a licensed engineer, or added square footage.
- What moves you up: moving plumbing stacks, raising ceilings, re-framing openings, replacing windows, adding a second HVAC zone, custom cabinetry, stone slab, and anything that needs engineering.
- What moves you down: keeping wet walls where they are, semi-custom cabinetry, porcelain tile instead of slab stone, reusing existing windows, and deciding every selection before the contract is signed.
What's Different About Renovating a House in Leander
Most of Leander's housing stock is production-built and relatively young — subdivisions off Crystal Falls Parkway, Ronald Reagan, Bagdad Road and the US 183 corridor largely went up from the 1990s onward, with older homes clustered near the original town center. That matters in a specific way: the bones are usually in reasonable shape, so the money goes into layout, cabinetry and finish rather than rot repair. The flip side is builder-grade everything — thin trim, laminate counters, hollow doors, undersized can lights and a kitchen walled off from the family room. A whole-home renovation in a 2004 Leander house is mostly about undoing those decisions.
Nearly all of these houses are slab-on-grade, single or two-story, with the plumbing cast into the slab. That is the single biggest cost lever on a Leander whole-home project. Moving a kitchen sink or a shower drain means cutting and patching concrete, which adds both dollars and days. We map every existing drain location during design so you can decide, with a price attached, whether a new layout is worth the slab work.
Central Texas climate shows up in the scope too. Hot summers push us toward attic insulation upgrades, duct sealing, and right-sized HVAC while the walls are open — it is the cheapest time in the life of the house to do it. Hard freezes happen here, so when we are already in the walls we route and insulate supply lines away from exterior wall cavities and attic runs where the design allows. Two-story Leander houses often have long duct runs to the upstairs bedrooms; if the second floor has never cooled properly, a whole-home renovation is the moment to fix the duct design instead of adding another window unit.
Many Leander neighborhoods are governed by an HOA with architectural review for anything that changes the exterior — roofline, windows, siding, driveway, patio covers. We treat HOA submittal as a scheduled task in the project plan, not an afterthought, because approval timing sits in front of exterior work.
Permits and Inspections
We handle permitting. Depending on your address, a Leander project is reviewed either by the City of Leander or by Williamson County, and some southern addresses with an Austin mailing address fall under City of Austin review. We confirm the authority having jurisdiction for your specific parcel during design and submit the drawings, the energy compliance paperwork and the subcontractor licensing documents for you.
A whole-home renovation usually involves a building permit plus trade permits for electrical, plumbing, mechanical and, where applicable, gas. Inspections are staged: rough-in for framing, electrical, plumbing and mechanical before insulation and drywall; insulation; then final inspections at the end of the job. Our schedule is built around those inspection holds, so they are already in the calendar you receive — not surprises that push your finish date.
If your plans involve removing or altering framing, raising a ceiling, or widening an opening, that determination is not ours or yours to make by eye. A licensed structural engineer evaluates it and the permit office approves the drawings. We coordinate the engineer, carry their detail into the construction documents, and build what gets approved.
Permit and review fees for a whole-home renovation in this area typically run $1,500–$5,000 depending on valuation and scope, and engineering, when needed, typically runs $1,500–$4,000. Both are itemized inside your fixed price before the contract is signed, so they are not a change order later.
The Timeline, in Weeks
People hear "4 to 8 months" and assume that is the whole project. It is not — that is construction. Here is the honest sequence from your first phone call to the final walkthrough. We do not promise a start date before a contract is signed and a permit is in hand.
Add it up and a realistic whole-home renovation runs roughly 7 to 13 months from first visit to final walkthrough, with 4 to 8 of those months being active construction. Most Leander families move out for a down-to-studs project; with the kitchen, both bathrooms and the HVAC out of service at the same time, staying put is rarely workable. Plan the rental or the relocation around the construction start, not the first meeting.
A useful reference point for scope inside the project: a bathroom is typically 3 to 5 weeks of work and a kitchen 6 to 10 weeks. In a whole-home job those overlap with each other and with flooring, paint and trim, which is exactly why one contractor running one schedule beats hiring four specialists in sequence.
- Week 1 — First visit at the house: we walk the rooms, measure, look at the slab plumbing and the panel, and talk budget honestly before anyone draws anything.
- Weeks 2–8 — Design and selections: floor plans, elevations, cabinetry layout, and every fixture, tile and appliance chosen. Nothing stays "to be decided."
- Weeks 6–10 — Fixed price in writing: a line-item contract based on finished drawings and real selections, not allowances that drift.
- Weeks 8–18 — Permitting, engineering if required, and HOA architectural review where applicable. Review timelines sit with the jurisdiction, so we track and follow up weekly.
- Weeks 18–50+ — Construction: demolition, rough-in trades, inspections, insulation and drywall, cabinetry, tile, flooring, trim, paint, fixtures, final inspections and punch list.
- Final week — Walkthrough, warranty documents, manuals, paint touch-up kit and the 5-year workmanship warranty in writing.
How Our Fixed-Price Design-Build Process Works
One contract covers design, permitting, demolition and construction. You are not managing an architect, a general contractor and four trades who each blame the other. Our carpenters are in-house employees, which is why framing, trim and cabinet installation stay on schedule and to one standard instead of waiting on whoever is available that week.
The fixed price is the point. We do not sign a contract off a sketch. We finish the drawings, you make every selection, and then we price it — materials, labor, permits, engineering, dumpsters, the lot. That number is in writing before demolition. The only things that change it are changes you request, or genuine concealed conditions behind the walls, and those come to you as a priced, signed change order before any work proceeds. Financing is available if you would rather not pull the full amount from savings.
Workmanship is covered by a 5-year warranty. Manufacturer warranties on appliances, fixtures and materials are documented and handed to you at closeout.
When you interview contractors in Leander — including us — ask these questions and compare the answers side by side.
- Is the price fixed in writing before demolition, or is it an estimate with allowances that can move?
- Who draws the plans, who submits the permit, and who attends the inspections?
- Are the carpenters employees or day-rate subs, and who is on site every day?
- What happens if the engineer's detail changes the framing plan — how is that priced?
- How many days per week will trades actually be in my house, and what is the schedule for inspection holds?
- What is covered by the workmanship warranty, for how long, and what voids it?
- Can I see the line-item scope, including permit fees, engineering and dumpsters, before I sign?
What to Do Next
Before you call anyone, write down three things: the rooms you want changed, the three problems with the house that bother you most, and the number you are genuinely willing to spend. Take photos of the electrical panel, the water heater, the HVAC condenser data plate, and each bathroom. If you have the original builder plat or plans, pull them out — on a Leander house from the 2000s they often still exist.
Then book a first visit. We will walk the house with you, tell you plainly whether your scope fits your budget, and if it does not, show you where the ranges above put you so you can decide before spending money on design. If the scope works, we move into design and selections, hand you a fixed price in writing, pull the permit, and build to the calendar we gave you.
Leander homeowners also ask
Can I live in my Leander house during a whole-home renovation?
For a down-to-studs project, almost never. The kitchen, bathrooms, HVAC and often the water service are out of use at the same time, and the dust from drywall and flooring work reaches every room. Plan on relocating for the 4 to 8 months of construction and budget for it. For a lighter $150,000–$250,000 whole-house refresh done in phases, staying is sometimes workable — we will tell you honestly which category your project is in at the first visit.
Who issues the permit for my Leander home — the city or Williamson County?
It depends on your parcel. Leander addresses inside the city limits are reviewed by the City of Leander, some are under Williamson County, and a few southern addresses fall under City of Austin review. We confirm the authority having jurisdiction for your specific address during design and handle the submittal, trade permits and inspection scheduling. Permit and review fees for a whole-home project typically run $1,500–$5,000 and are itemized in your fixed price.
Can I open up the wall between my kitchen and living room?
That is a question for a licensed structural engineer and the permit office, not something anyone should answer by looking at it. If you want the opening, we bring an engineer in during design, carry their detail into the permit drawings, and price the work before you sign. Engineering for a job like this typically runs $1,500–$4,000, and it is in the fixed price rather than showing up later as a change order.
Why does design and permitting take so long before work starts?
Because that is what makes the construction calendar real. Finished drawings and completed selections let us price the job as a fixed number instead of allowances that drift, and the permit has to be in hand before demolition. Design and selections typically take 4 to 8 weeks, permitting and any HOA architectural review another 4 to 10 weeks. Front-loading that work is why the construction schedule we hand you is the one we build to.
Check it with Leander’s own pages
Permit rules and fees change, and the office that issues the permit is the authority on them, not this guide. These are its pages.