Whole-Home Renovation in Pflugerville, TX: 2026 Cost Guide
A down-to-studs whole-home renovation in Pflugerville generally runs $180,000-$275,000 for a full cosmetic and systems refresh inside the existing footprint, $275,000-$450,000 once layouts change and plumbing and electrical move, and $450,000 and up for high-end finishes, custom cabinetry throughout, or added square footage. Construction takes 4 to 8 months once demolition starts, with design and permitting handled before that. You get one contract, one schedule and one fixed price in writing before anybody swings a hammer.
Already planning a whole-home renovation? Get a real price for your house →

What a whole-home renovation costs in Pflugerville
Whole-home pricing is driven by three things: how much of the house you touch, whether walls and plumbing move, and the finish level you pick. A 1,900-square-foot Pflugerville tract home getting new floors, paint, trim, doors, lighting, a rebuilt kitchen and two reworked bathrooms sits near the bottom of the range. The same house taken to the studs with a reconfigured floor plan, relocated laundry, new HVAC and a primary suite rebuild sits near the top.
The kitchen is usually the single largest line item, and our published Austin-area kitchen ranges apply here: $45,000-$70,000 for a refresh in the existing footprint with new cabinets, counters, lighting and fixtures; $70,000-$110,000 when the layout opens up and plumbing moves; $110,000 and up for a high-end kitchen taken down to the studs with custom cabinetry and high-end appliances. Bathrooms, flooring, the HVAC and electrical scope, and exterior work stack on top of that.
Every number you see here is a planning range. The number that matters is the fixed price we put in writing after design, and it does not move unless you change the scope.
- Moves cost up: relocating a kitchen or laundry, adding a bathroom, raising ceilings, custom cabinetry in multiple rooms, full window replacement, a new HVAC system with redesigned duct runs, a re-roof, hardwood through the whole first floor.
- Moves cost down: keeping plumbing fixtures where they are, reusing the existing kitchen footprint, semi-custom cabinets, porcelain tile that reads like stone, painting existing solid-core doors instead of replacing them, phasing the exterior for a later year.
- Plan for 8-12% of the construction budget as a contingency for conditions found behind drywall, especially in older homes near downtown Pflugerville.
What's particular about renovating Pflugerville houses
Most of Pflugerville's housing stock is suburban subdivision construction from the 1990s through the 2010s: slab-on-grade foundations, wood-frame walls, brick or masonry veneer on the front with fiber-cement or hardboard siding elsewhere, trusses overhead and HVAC equipment and ductwork in the attic. That combination shapes almost every decision in a gut renovation.
Because the slab is the floor, moving a shower, a sink or a kitchen island means cutting and re-pouring concrete. It is routine work and we do it on most whole-home jobs, but it changes the price and it changes the sequence, so we decide it during design, not during demolition. Attic-mounted mechanicals mean duct replacement and better attic insulation are easy to fold in while the ceilings are open, and in a Central Texas summer that is the upgrade people notice most.
There is a smaller pocket of older homes near downtown and the Pecan Street area. Those come with their own list: original wiring and plumbing, smaller closets, lower ceilings in additions built over the decades, and finishes that need testing before demolition in anything built before 1978. We budget for that testing up front rather than discovering it mid-job.
Two more Pflugerville specifics worth planning around. Many neighborhoods have an active HOA, and exterior changes such as siding color, window style, a new covered patio or a driveway extension usually need HOA architectural approval on top of the permit; we will tell you what to submit and when. And expansive clay soils are common across this part of Travis County, so if your house shows movement, cracked tile lines or sticking doors, a licensed structural engineer evaluates the foundation before we price interior finishes that depend on it.
Permits and inspections for a Pflugerville renovation
Which office reviews your plans depends on your address. If your home is inside Pflugerville city limits, the City of Pflugerville's development services and building inspections department handles the residential building permit and the inspections; if you are outside the city in unincorporated Travis County, the county handles it. We confirm the jurisdiction from your address and parcel before we price the job, and we handle the submittal, the comment responses and the inspection scheduling as part of the contract. We also handle City of Austin permitting for our clients inside Austin, so the process is the same either way.
A whole-home renovation typically pulls a residential building permit with electrical, plumbing and mechanical trade permits under it. Expect a permit and plan review package in the $1,500-$4,000 range for a typical Pflugerville whole-home scope, more if you are adding square footage and drainage or impervious cover review comes into play. Those fees are itemized in your fixed-price contract so there are no surprises mid-build.
Two things we never decide for you. Whether a particular wall can be removed or modified is determined by a licensed structural engineer and confirmed by the permit office through the plan review and inspection process, and we price the engineered detail once that answer is in hand. And whether a specific piece of work needs a permit is the permit office's call, not ours or yours. We ask the question in writing during design so the answer arrives before demolition instead of after.
- Ask any contractor: which jurisdiction is my address in, who pulls the permit, and whose name is on it?
- Inspections you'll typically see: rough electrical, rough plumbing, rough mechanical, framing, insulation, then final inspections for each trade before occupancy of the finished space.
- If you're adding a room, allow extra review time for the site plan, setbacks and drainage review.
- HOA architectural review runs on its own calendar and is separate from the permit; start it early.
A realistic timeline, first visit to final walkthrough
Whole-home construction is 4 to 8 months in Pflugerville. Add the design and permitting phase in front of it and most projects run 7 to 11 months from the first phone call to the final walkthrough. We publish the calendar before demolition and build to it, because design and permitting are finished first.
Here is the shape of it. The exact week counts depend on scope, plan review turnaround and whether you are living in the house during construction. We will not promise a start date before your permit is in hand.
Living on site is possible on some phased whole-home jobs, but a true down-to-studs renovation with the kitchen, both bathrooms and the HVAC out of service is not a house you can live in. Most Pflugerville clients rent for the construction window, and we would rather you budget that line from day one than find out in month two.
- Weeks 1-2: first visit, measure and walk the house, scope conversation, preliminary budget range.
- Weeks 2-8: design development, structural engineering if the plan calls for it, selections for cabinets, tile, counters, plumbing and lighting, then your fixed price in writing.
- Weeks 6-14: permit submittal and plan review, HOA approval in parallel, long-lead items ordered (windows, cabinets and appliances are the usual holdups).
- Weeks 1-3 of construction: demolition, dumpsters, abatement if testing called for it, slab cutting where plumbing moves.
- Weeks 3-10: framing changes, rough plumbing, rough electrical, HVAC and ductwork, rough inspections.
- Weeks 10-18: insulation, drywall, interior trim and doors, cabinets, tile.
- Weeks 18-28: counters, paint, flooring, plumbing and lighting fixtures, appliances, final inspections, punch list and final walkthrough.
How our fixed-price design-build process works
One company does the design, the permitting and the construction, so there is nobody to blame when a detail falls between drawings and framing. We start with a visit to your Pflugerville home, measure what is there and talk through what you want the house to do. You get a preliminary budget range at that stage, honestly wide, because we have not drawn anything yet.
Then we design. Floor plans, elevations, a selections list down to the cabinet door style and the tile size, and engineering where the plan requires it. When the drawings and selections are locked, we hand you a fixed price in writing with the scope itemized, allowances spelled out, permit fees included and a construction calendar attached. That number holds unless you change the scope, and a change order is written and priced before the work happens.
Our carpenters are in-house, not day-rate subs rotating off the job. The framing, trim, doors and cabinet installation are done by people on our payroll, with licensed electrical, plumbing and mechanical trades we use repeatedly. The workmanship warranty runs five years, in writing, separate from the manufacturer warranties on your appliances, windows and fixtures. Financing is available if you would rather not tie up cash during the build.
When you talk to any contractor in Pflugerville, ask these: Is the price fixed or cost-plus, and what triggers a change order? Who pulls the permit and schedules inspections? Are allowances listed line by line, and what happens if I pick something above the allowance? How many jobs will your crew be running at the same time as mine? What exactly does the workmanship warranty cover, and for how long? Get the answers in writing.
What to do next
Pull together three things before you call anyone: a rough square footage and the year your house was built, a short list of what has to change versus what would be nice, and a number you are comfortable spending. If you have your builder's original floor plan or a survey, dig it out, it saves design time.
Then book a walkthrough. We will measure the house, flag the Pflugerville-specific items we see from the street and the attic hatch, tell you which jurisdiction reviews your permit, and give you a budget range the same visit. If the range works, we move into design and you get the fixed price and the calendar before demolition day.
Pflugerville homeowners also ask
Can I live in my Pflugerville house during a whole-home renovation?
Usually not for a true down-to-studs project. When the kitchen, bathrooms and HVAC are out of service at the same time, the house is not habitable, and that is 4 to 8 months of construction. Some phased renovations let you stay in one wing while we work on the other, which adds time to the schedule and cost for temporary protection and dust control. Decide this during design so the budget reflects it.
Who issues the permit for my renovation, Pflugerville or Travis County?
It depends on your address. Homes inside Pflugerville city limits are permitted and inspected through the City of Pflugerville; homes outside the city in unincorporated Travis County go through the county. We confirm the jurisdiction from your parcel before pricing and handle the submittal, plan review comments and inspection scheduling as part of your contract. We handle City of Austin permits the same way for clients inside Austin.
Can we take out the wall between the kitchen and living room?
That is not a call we make from a walkthrough. A licensed structural engineer evaluates the framing and the roof load path and specifies what is needed, and the permit office confirms it through plan review and the framing inspection. We bring the engineer in during design, price the detail once we have their drawing, and pull the permit for it. That sequence is also why this gets settled before demolition rather than during it.
How accurate is the fixed price, really?
The fixed price is written after design is complete and selections are made, so it is built on actual drawings and actual products, not a per-square-foot guess. It holds unless you change the scope, and any change order is written and priced before that work starts. The two things we cannot see through drywall and concrete are old plumbing and wiring conditions in pre-1990 homes, which is why we recommend an 8-12% contingency you control.
Check it with Pflugerville’s own pages
Permit rules and fees change, and the office that issues the permit is the authority on them, not this guide. These are its pages.